The exact number of nights required will depend on the progress of the work, but the second week of closures may begin on Sunday night, October 26.
Contractor Fluor-United and its sub-contractors are managing the complex operation.
Detour Routes for I-26 Traffic
Drivers should be aware of the following detour routes, which are in place while the old bridge segments are removed. Additional signage has been placed to assist drivers, particularly those unfamiliar with the area. NCDOT is programming traffic signals on the detour routes with longer green lights to help manage the flow of traffic.
I-26 West Detour
Sunday Night (Oct 19) through Wednesday Night: Traffic will be diverted at Airport Road (Exit 40), then directed north onto Hendersonville Road (U.S. 25) to I-40. Drivers may also be directed, if necessary, to N.C. 191 and I-240 East.
Thursday Night: Traffic will be diverted at U.S. 25 (Exit 44).
I-26 East Detour
All Nights: Traffic will be diverted at Brevard Road (Exit 33), then directed west onto Long Shoals Road (N.C. 146), which leads back to I-26 East.
Blue Ridge Parkway Remains Open
The new Blue Ridge Parkway bridge will remain open during these operations. While there may be short delays related to the construction activity or typical autumn traffic, the Parkway itself will not be closed.